²ÝÝ®ÊÓƵAPP

Return
Location:
Holtwood, PA
Completed:
2016

Holtwood Obermeyer Spill Gate Installation

Scope of Work
²ÝÝ®ÊÓƵAPP installed a temporary debris/access platform and steel cofferdam to dewater Sections 2 and 3 of the Holtwood Dam to facilitate the demolition of the existing Bridgestone rubber dam, concrete, and embedded utilities on the crest of the spillway. 
Project Details
  • Installed approximately 710 linear feet of steel sheet pile cofferdam fastened to the upstream face of the dam supported by a bent-plate ledger, as well as a downstream steel-supported access/debris platform with timber decking
  • Performed tremie seal to sheet pile flutes and cofferdam closure walls
  • Demolished/removed approximately 1000 linear feet of Bridgestone rubber dam, as well as exiting concrete and embedded items in spillway Sections 2 and 3
  • Installed pier junction boxes, as well as approximately 2850 linear feet of 1 inch embedded conduit, wiring, and control cable
  • Installed approximately 1800 linear feet of 4 inch embedded galvanized Victaulic air piping, including 36ea risers for the new Obermeyer air bladders
  • Placed approximately 1000 cubic yards of concrete via slick line and concrete buckets, including resurfacing of a portion of the upstream crest
  • Installed 700 linear feet new Obermeyer inflatable flashboard system, including 36 rubber bladder/steel gate sections, 4 embedded abutment plates, main anchor assembly, and associated restraining components
Lean, Innovative and Unique Project Solutions
Talen Energy’s permit for construction was set to expire in December of 2015, which significantly constrained the required project completion date. However, early in the project, the addition of the upstream crest resurfacing scope, paired with difficult river conditions early in the project, prompted Talen Energy to request an accelerated schedule. ²ÝÝ®ÊÓƵAPP was able to compress the project duration by two months. Early coordination, collaboration, and planning between ²ÝÝ®ÊÓƵAPP, HDR, and Talen Energy enabled the team to develop a cofferdam design that would meet permit requirements, facilitate open access for the upstream crest work, and eliminate pile driving for risk of disturbing a submarine cable running along the face of the dam. 
No items found.
VIDEO: A Pre-Winter Completion

Our Offices
Corporate Headquarters
P.O. Box 1000
Pittsfield, ME 04967
207-487-3311
info@cianbro.com

Email Us

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.